Close

Ongoing Projects

  1. Home
  2. /
  3. Projects
  4. /
  5. Ongoing Projects

CME DEPARTMENT

Sr.No. Description of the issue Present Status
1 SITC of 05 nos. of 100 MT capacity road weighbridges Out of 5 WBs, 02 have been installed and commissioned on 30.01.2026 remaining 03 WBs, Site will be handed over upon confirmation from the Traffic Department
2 DSITC of Firefighting system and associated facilities including Operation & Maintenance at OJ-8 Complete Firefighting system installed at Oil Jetty No 08, Same inspected by PESO representative on 22.08.2025 awaiting for PESO final approval
3 SITC of 08 Nos. Quick Release Mooring Hook (QRMH) at OJ-08 All 08 Nos of QRMHs installed at site OJ-08
4 Revamping and Upgradation of Firefighting system and associated facilities at Oil Jetty Area- SITC of water Pump set/water Pumping system (Task-1) All VT Pumps were installed at site & Final testing of VT pumps with firefighting pipeline is under progress
5 Revamping and Upgradation of Firefighting system and associated facilities at Oil Jetty Area- SITC of firefighting system and Associated facilities along with Pipelines, Civil, Structural, Instrumentation, Electrical and allied works (Task-2) Equipment’s in Pump House and Control room including electrical and instrumentation installation work, is under Progress

 

CIVIL DEPARTMENT

Sr.No. Description of the issue Present Status
1 Up-gradation of Road from junction of tuna jetty Road to Take off point at tuna tekra work is in progress.
2 Construction of Common connecting platform of OJ 9 to 11 work is in progress.
3 Supply and Stacking of Quarry material/Granular Material at Stacking Yard At Kandla work is in progress.
4 Excavation/cutting in Water Front Area at Roll-on/Roll off(Ro-Ro) ,facilities for Handling of ODC cargo at Bunder Basin work is in progress.
5 Retrofitting of Existing Cargo Berth No. 10 (Panel 77 to 85) & Remaining Portion of Cargo Berth No 7 (Panel 51 to 55 work is in progress.
6 Allotment of Plot No 49 of SIPC location-2 laying of Water supply line till boundary of Plot no 49 work is in progress.
7 Construction of SWD for cleaning water logging near liquid tank terminal at Old Kandla work is in progress.
8 Providing & Laying of chemical product pipeline from OJ 7 to Y Junction inside OJ Complex work is in progress.
9 Providing Asphalt Approach Road to Pipelines for safety and security purpose from Oil Jetty to Kharirohar alongside pipeline(Phase-I). work is in progress.
10 Supply and Transportation of water at Kandla, Tuna and Gandhidham for a period of Two years. work is in progress.
11 Providing Precast folding RCC compounf wall at Mitha Port, Old Kandla. work is in progress.
12 Request for proposal for appointment of Consultant for preparation of DPR, Planning and Designing for 100 MLD Capacity Desalination plant expandable to 300 MLD work is in progress.
13 Development of Geospatial Port Land Management Information System for Deendayal Port Authority, Kandla, Gujarat work is in progress.
14 Construction of Shopping Complex at Gopalpuri work is in progress.
15 S/R to Sports Complex at Port colony Gopalpuri, Gandhidham. work is in progress.
16 Construction of Conference Hall at A.O. Building, Gandhidham. work is in progress.
17 Construction of “E” TYPE quarters at Port Colony Gopalpuri, Gandhidham. work is in progress.
18 Construction of new Guest House construction behind Dr. Babasaheb Ambhdhkar Hall. work is in progress.
19 CSR work of construction of Police Community Hall at Police Headquarters Shinay. work is in progress.
20 CSR work at Hari Aasro Trust- Adipur, Kastuba Gandhi Balika Vidhyalay – Shinay work is in progress.
21 Improving / Upgradation of parking yards situated on north of road leading to WG-1 to WG-2 outside cargo jetty area. work is in progress.
22 Raising and upgradation of plots inside cargo jetty area work is in progress.
23 Raising & upgrading the RCC Plots adjoining to track no.10, 11 & 12 work is in progress.
24 Providing RCC cable trench for electric cables inside cargo jetty area. work is in progress.
25 Providing internal roads in backup area of berth No. 11 and 12. Renamed as Upgradation of Back up area of berth No. 11 and 12 work is in progress.
26 Construction of Office Accommodation for CISF at Kandla renamed Construction of Office accommodation for Port Staff work is in progress.
27 Upgradation of backup area of Cargo Berth No 16 inside Cargo Jetty area. work is in progress.
28 Development of plots, roads & SWD in 66 hectare area inside CJ Area Renamed as “Upgradation of plots, roads & S.W.D. In 66 hectare area inside cargo jetty area work is in progress.
29 Development of area from chainage 13.5 Km to take off point including R&D yard to facilitate upcoming new projects at Tekra work is in progress.
30 Extension of existing line by 750 m towards Kutch Salt Junction on the line leading to Berth No. 13 to 16 (Work awarded to M/s IPRRCL on Deposit Work) work is in progress.
31 Improving fendering arrangement at cargo berth no. 15 work is in progress.
32 Construction of RoB in Lieu of existing LC-1A at 363.625 KM on NH-8A KFTZ-Kandla Road in state of Gujarat (NH Division, Gandhidham (Work awarded to NHD on Deposit Work)) work is in progress.
33 Construction of Rest Shelter & Toilet block at Berth No. 13 & 16 work is in progress.
34 Resurfacing of road network and parking plot in Liquid storage tank at Kandla work is in progress.
35 Providing Cattle traps at gates of cargo jetty area.” work is in progress.
36 Special Repairs to Pontoons and Walkways of SNA Jetty work is in progress.
37 Augmentation of liquid Cargo Handling Capacity from 8 MMTPA to 10 MMTPA through Modernization of existing Pipeline network at Oil Jetty area Renamed as – Replacement & Revamping of Pipeline network at Oil jetty area at Kandla work is in progress.
38 Appointment of Consultant for Establishing PMU for Procurement, Monitoring, Implementation and Administrative Support at DPA work is in progress.
39 Construction of New Seafarer building at Kandla-Cargo berth area. work is in progress.
40 Engagement of Consultant For Development Of Multi-Speciality Hospital And Nursing College At Gandhidham work is in progress.
41 Appointment of Marine Consultant For the Work of Construction of Mooring Launch Floating Platform/ Pontoon and Connecting Platform/walkway at Oil Jetty No.07 work is in progress.
42 Appointment Of Marine Consultant For Work Of Modification Of SNA Jetty work is in progress.
43 Upgradation of fender for cargo berth 1 to 6 at Deendayal Port work is in progress.
44 Construction of Port Office Building at Kandla work is in progress.
45 SWD Outside Custom Bounded Area work is in progress.
46 Appointment of consultant for strengthening /Upgradation of Oil Jetty 1,2,4 in Kandla work is in progress.
47 Widening and Improvement of KKRoad work is in progress.
48 Construction of ROB@ LC236B work is in progress.
49 (Deposit ) : IPRCL work is in progress.
50 Construction of ROB@ LC235 work is in progress.
51 (Deposit ) : Western Railway work is in progress.
52 Development of sides of all major roads by providing footpath, pitching for side, strengthening and all allied works. work is in progress.
53 Strengthening of existing environmental management cell of DPA : appointment of environment expert for two years and further extendable for one years. work is in progress.
54 Preparing and monitoring of Environmental monitoring and management plan for DPA at Dahej, Hazira and Ghogha work is in progress.
55 Preparing and monitoring of Environmental monitoring and management plan for DPA at Dahej, Hazira and Ghogha work is in progress.
56 Regular monitoring of Marine ecology in and around the DPA and continuous monitoring programme covering physico-chemical parameter of marine water and marine sediment samples work is in progress.
57 Studies on dredged materials or presence of contaminant (EC&CRZ clearance accorded by the MoEF&CC, GOI dated 19/12/2016 – specific condition no. vii work is in progress.
58 Maintenance of Green Belt development in DPA (Phase II) work is in progress.
59 Green Belt Development in DPA and its surrounding area (Phase III) work is in progress.
60 Regular monitoring of Mangrove Plantation in an area of 1650 Hectares for Deendayal Port Authority work is in progress.
61 To Demarcate Ecologically Sensitive Area (ESA) as per CRZ Notification work is in progress.
62 ISO 14001 certification for providing port facility and related maritime services for vessels and Cargo Handling including storage work is in progress.
63 “Continual Improvement of ISO 14001:2015 Environmental Management System of Deendayal Port Authority for the period of two years” work is in progress.
64 Preparation of Site-Specific Conservation Plan & Wildlife Management Plan for implementation of stipulated condition of Environment & CRZ Clearances work is in progress.
65 Transition of Business Operations to Water Neutrality – Water Neutrality of Deendayal Port, Kandla (Phase II) -Installation of Atmospheric Water Generator (AWG) Machines at DPA work is in progress.
66 Monitoring of Ambient Air Quality in the Port Area of Deendayal Port Authority through Continuous Ambient Air Quality Monitoring System (CAAQMS) for a period of 3 years work is in progress.
67 Obtaining Environmental & CRZ Clearance for the proposal “Development of setting up of Integrated ship building cluster at Deendayal Port Authority, Kandla” work is in progress.
68 Obtaining Environmental & CRZ Clearance for the proposal “Development of setting up of Integrated ship building cluster at Deendayal Port Authority, Kandla” work is in progress.
69 Obtaining Re-CRZ Clearance for the proposal “Development of Out Fitting Jetty & Floating Dry Dock Complex with allied infrastructure at DPA waters at OOT, Vadiinar, Gujarat” – reg. work is in progress.
70 Development of Container Terminal at Tuna-Tekra, Deendayal Port on BOT basis under PPP mode work is in progress.
71 Development of Oil Jetty to handle liquid cargo and ship bunkering terminal at Old Kandla on BOT basis work is in progress.
72 Development of Marine Liquid Terminal Facilities consisting of SPM & Two Product Jetties in KPT Waters at OOT, Vadinar , Kandla Port on Captive Use Basis work is in progress.

Color